on 06-10-2010 9:07 AM
Hi there.
I need following information:
When we creating PR, system gives delivery date as today's date. If we created PR without material, account assingment(F) and entered the Pln. delivery time is system calculate Pln. delivery time and gives delivery date? If yes how this changes will happen? do we do the configuration?
Thanks,
Raj
It is standard process.
if you maintain planned delivery time , system adds the planned deliver time to the present date and gives delivery date
In layout local settings may be and fixed the delivery date as present date, so it is showing delivery date by default when you enter the screen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for quick reply.
Could you please let me know where do we maintain Pln. Delivery time?
I know in Material Master and Vendor Master. In this case I am and creating Pr with Materail no#. and vendor Master no maintained.
Without maintaining in the both master data, If i entered Pln. Delivery time at the time of PR creation, system adds and give the correct delivery date?
Thanks
Raj