Hi ALL,

In Sales order Schedule line(after clicking shipping i.e displaying bottom of the screen) material availabity date is coming incorrectly . In my material in mrp2 view i selected proceument type as F and i gave planned delivery time as 19 days and GR processing days as 1 . suppose if i am putting sales order as on today 9-6-2010 it should show material avaialbity date as

7-7-2010 but it is showing 10 days more (excluding saturday and sunday) . So please give me suggestion where to check in the program SAPMV45A.