MB21 No Cost Updation

Hi Experts

We are trying to reserve material using MB21 against WBS but after reservation no plan cost updated? Please tell me if anything is missing?

Atif

Edited by: Virendra Pal on Jun 8, 2010 8:56 AM

No capitals please - title corrected

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Jun 08, 2010 at 07:55 AM

    Manual reservation will not update cost in project. If you plan it through network activities by assigning material to it, then you can see the cost in project.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 09, 2010 at 09:43 AM

    I agree with Ahmed. Thanks for your reply...