I have a material A - Coil, generally comes in a roll of 1 ton, 2 ton etc.

I want to cut three different material B, C & D from the same coil.

Can we create a single SC Order and one challan, to issue the Material A and receipt of Material B,C & D which have different weigth the rate of cutting (SC Charges) is same.

How to handleded this situation in SAP ???

I our previous ERP (Baan), I was creating, three BOM, 3 SC Ordres for, Material A, B & C . 3 Different challan for Issuing the Material A, B & C. Physically one coil is sending to the SC Against three challan.