on 06-05-2010 9:40 AM
Hi Experts,
We are planning costs in WBS through ECP.But in any of the reports (Eg-CN41,S_ALR_87013531,S_ALR_87013532 ) this cost is not appearing.
We have activated multiple co versions for ECP.Is it affecting any thing? or any other settings to be maintained??
Thanks for the answar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Which CO version are you using for ECP?...If it is other than 0, then input the corresponding CO Version during execution of report....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for the reply,After executing cjen the ECP cost is appearing in all reports for the particular project.
But when I created a new project & made ECP it is not appearing in reports.(It may also appear after cjen) Is it necessary to reconstruct data base every time for a new project ?? Is there any one time setting ??