Time Based ATD for Deployment

Hi Gurus,

We are having a customer requirement where we want to consider only Stock for TLB which is daily and for giving long term visibility should do deployment for 2 weeks considering Stock+Expected Production.

So we are thinking of Deployment Run Weekly...considering Stock+Expected Production...which will consider that and create Confirmed STR...

And Intend to run TLB daily only on STOCK..........as i understand TLB will club confirmed STR's ....will not look at Stock while STR's ..........

Or Other option Run Deployment / TLB daily...where wanted to have Deployment daily ....where ATR should have time phased ...like for 1 day only Stock and from 2nd day onwards Production Order + Planned Order.....Wanted to have a Time phased ATR kind of Concept

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Jun 04, 2010 at 06:01 AM

    Hi Priya,

    Your second option looks very realistic for implementation.

    Because when you run deployment/TLB, the load building

    will be at a very optimal level based on that day's constraints

    and priorities. Hence running daily looks more predominent

    Regards

    R. Senthil Mareeswaran.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 26, 2010 at 12:29 PM

    Hi Priya,

    I have same kind of scenario and need to deploy SNP Planned orders. Did you get any information on time based deployment.

    Thanks & Regards,

    Chetan

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 26, 2010 at 06:01 PM

    Interesting scenario. You can write a macro for this. Add a key figure to your planning book for ATR. Now this key fig will be updated by the macro. You can write the macro based on the logic that for day one it will update the ATR key fig, considering the value @stock key fig,.. afetr that it will update the value by adding stockPln ord...

    Hope this helps.

    Thanks,

    Satyajit

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Somnath Manna

      Hi Somnath,

      Its always great to hear from you.

      Yes Category Group assigned determines ATD Receipts. But its still the 1st level of interface, so I think a Macro can modify the ATD value.

      She need to run the macro before the deployment job, so that it will have modified ATR value while deploying.

      Thanks,

      Satyajit

  • Oct 17, 2012 at 10:26 AM

    Priya,

    I am on a new project in the UK and have the same requirement today as you started back in 2010.  Can you reply as to which approach you followed and were there any lessons you could share.

    Thanks in advance

    Paul