on 06-03-2010 4:54 AM
Dear Experts,
In the maintenance plant strategy, is it sufficient to mention the calendar details only for 'Time-keydate ' , and ' Factory Calendor' indicatore . Or we need to mention for ' Time ' also ?
You are absolutely right that for Time -Factory Calendar and Tiime- Key Date, you have to specify the Calendar. In case factory calendar has not been specified in the Maintenance Plan, then the factory calendar would be derived from the settings you have maintained at Plant Level and for Only "Time" Scheduling Indicator there is no need to give the factory Calendar. You can also change the factory calendar for Scheduling Indicator Time-Factory Calendar and Time - Key Date.
Edited by: Usman Kahoot on Jun 3, 2010 1:40 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case of Time - Factory Calander strategy indicator used, factory calander needs to be given. Else factory calander wont be considered.
Regards,
Maheswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.