Hi Experts ,

Is is possible to control the Lower level wbs elements from doing confirmations/ posting actual costs or any goods issue when the the project is budgeted at only top level and the budget is not distributed to the lower level wbs elements.

The status of entire porject is Released .

The budget is released only for the top level wbs elements and Status AVAC is active for all the lower level wbs elements.

Please suggest.