Dear experts,
Could You tell me how availability control works when working on budget? The sytuation:
my user deactivated availability control, and needs to do few budget operations on WBS. First is decrease budget to level lower than actual costs. It is not possible because of availability control, but on this WBS we are able to make costs higher than budget. Is this standard behavior? Is there any configuration of availability control?
Thanks in advance.
Michael.
Hi again,
First I have to thanks for Your posts. I read everything You suggested. We have defined ++ as a business transaction group in customizing for tolerance limits. As I understand when user deactivate availability control it should be possible to change budget, even to level lower than actual costs. Am I right?
Regards.
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It depends on your budget profile....suppose, you have set availability control to be active once budget is allocated and then you have deactivated your Avail control manually...but if you go to CJ30/CJ32 to reduce your budget..during save of budget, the avail contril will get activated once again and will say budget error(if it is less than assigned value).
I would suggest you to read SAP HELP about project budget and availability control...It will help you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Michael!
Please, take a look at the following SAP Notes:
Note 1081758 - FAQ: Budget Check/Display
Note 783161 - Availability control check only if assigned value increases
Note 447102 - Availability control messages for goods movements
Note 602769 - Availability control checks despite deactivation
Note 1245966 - Activating the availability control for activation type 1
I think they might help you.
Regards,
Ivanna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As you said the user has deactiviated AVAC. That is the reason you are able to post costs higher than that specified in the budget. As far as configuration for budget is concerned i would suggest you to search the forum. There are a lot of threads on this topic.
Besides you can even go through SAP Help.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.