Problem with scheduling date

Former Member
0 Kudos

We have a preventive maintenance plan with the package 6 months . When I give the start of cycle date as 11/11/2009, system scheduling the next call date as 11/11/2010 instead of 11/05/2010. This problem occurring only when starting the cycle. What may be the problem ?

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

SAP CAT

1. Check to see if there any Offsets against the Package

2. Check the Package is actually 6M

3. Check your factory calendar

PeteA

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi SAP.CAT ,

What are the scheduling parameters you are maintaining?

Vivek

Former Member
0 Kudos

Dear Vivek,

All scheduling parameters are defined correctly , like Horizon 90% , for 3 years , with completeion date requirement.