on 05-31-2010 10:07 AM
We have a preventive maintenance plan with the package 6 months . When I give the start of cycle date as 11/11/2009, system scheduling the next call date as 11/11/2010 instead of 11/05/2010. This problem occurring only when starting the cycle. What may be the problem ?
SAP CAT
1. Check to see if there any Offsets against the Package
2. Check the Package is actually 6M
3. Check your factory calendar
PeteA