Dear Friends,

When creating maintenance order , i try to select the general task list already created through Extras - > Tasklist -- >General task lists. But in selection criteria the report already defaulted with the plant and the status as 2 and greyed out ( Actually required is 4 ) . Because of this some of the relevant tasklists are not selected . How to change this and to display all the tasklist .