Subcontracting without component

Hi all.

I need to design a flow where a supplier perform the software configuration of a product. We have a routing like this:

10 - assembly (internal)

20 - software config. (external)

30 - packaging (internal)

Our supplier performs the configuration by remote: we just need to connect the product to the internet and then supplier can setup it online.

Is it possible to manage a subcontract without goods issues/receipts?

Thanks,

Mauro

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jan 30 at 12:22 PM

    Hi Mauro,

    You can also maintain all the charges as subcontracting charges as line item in PO, and maintained text to describe the charges!

    Thanks,

    Add comment
    10|10000 characters needed characters exceeded

  • Jan 23 at 06:40 PM

    Hello

    Yes, this is possible.

    You should set a control key for subcontracting (such as PP03) for operation 20 on your routing and you should not assign any component to your operation.

    You will have to perform a MIGO for the subcontracting PO, but as those external processing POs do not carry a reference to the material, you won't be posting an actual goods receipt. The goods receipt will only happen when you finish your production order.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 21 at 09:59 AM

    Hello,

    This seems to be more related to service PO than subcontracting.

    Thanks.