on 05-28-2010 6:11 AM
Hi experts,
Is it possible to scrap raw materials from shopfloor and issue raw materials for the same order.....scenario is i need raw materials X and Y 100kg each to make 200kg of Z....I confirmed the order and materials X & Y came to the shopfloor....bfr production 20kg of X got spoiled by some reason....Is it possible to scrap the 20kg of X and issue 20kg w.r.t the same order without canceling the confirmation......
Regards,
Joseph.
Dear ,
It is very much possible to issue the material X .Wha you need to do is that goto CO02-Compoenet overview -Include X in Componenet line item -provide item categoer L and it will pop up with operation where to be assingened -then select the line item and hit the Cost calulator at header -does material availabilty chek - system will do reservation in the back ground
Now goto -migo or mb1a - issue agaisnt 261 for the order reservation
I think if you are scrping this material then u need to reieve the material aginst 551 to inventory and then re-issue against 261 against one of the operation for production order if u do not hit clear reservation in co11n .
Hope this is clear
Regards
JH
Edited by: Jiaul Haque on May 28, 2010 12:59 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Joseph,
It is possible to scrap the raw materials. First thing do u want to have the stock of the scrap materials then do the 262 mvt type for that material in mb1a and post it to the scrap storage location so that identification will be there. if donot want to have stock then donot reverse it so the cost of that material will be loaded to production order. You can issue the required material to the production order by 261 directly or create the reservation and then issue it. No need to cancel the confirmation. Hope this helps
regards
ramakant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Joseph,
If you dont want to cancel the confirmation, then using MB1A transaction 261 movement additionally you would be able to Issue additional quantity as required by you.
To your question of how to create reservation against order, in the change mode of the order in the component overview screen you need to manually the component another line and save the order. Now system in background would update the existing order reservation with a new line item.
Regards,
Prasobh
Hi Joseph,
Manual reservation i tried against order its not allowing, better you issue directly to production order. If you are using backflusing then if you add in component then u need to confirm the operation againt to do the GI manual issue against production order reservation it will not allow. I think its better to issue to produciton order directly it is treated as unplanned issue
hope it helps
regards
ramakant
Joseph,
Please follow the steps below,
1. Execute transaction MB1A.
2. Enter posting date, Plant, storage location and movement type 261 and then press enter.
3. In the next screen enter the Process order number, Component material number, quantity, storage location, batch if its batch managed and then save. Your unplanned goods Issue is completed.
Please let me know if you are getting any error in the above steps..
Regards,
Prasobh
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.