Manual dispatching of process orders in CM25

494 Views

Hi All,

I have scenario here.

I cannot dispatch the process order manually from order pool to work center pool in CM25. However it allows me to dispatch the same using the dispatch function available on the planning table.

Also in work center pool i am not able to reschedule the process order manually by dragging.

Please help me to resolve this issue.

Many thanks in advance.

Regards,

Sachin