Skip to Content

Modifying GOA documents in SRM

Hello all, why if I change GOA document in SRM, changes don´t pass to backend system? I checked BD87 transaction and IDOCS were generated OK but GOA's header value was not updated.

IDOC generated with changes has as VPREI, PREIS values 34 and must be 89.

How can I do?

Thanks in advance

Rosa Rodríguez

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 27, 2010 at 02:07 PM

    Hi Rosa,

    Please manually run update reports CLEAN_REQREQ_UP and BBP_GET_STATUS_2.

    FM BBPV_CONTRACT_TRANSFER is the FM should be responsible.

    Also I found something on service lines of a contract which might be of help

    The price on service line

    level is not, and can not be updated automaticaly by the system.

    For to realise that, it would be necesary to run a report everyday

    which dates all the contracts up. This would mean a lot of unnecesary

    resources. If you create a document with reference to the contract, the

    system takes the valid price anyhow from the header and not the price

    from the service line.

    Unfortunately SAP does not have standard report to update service

    lines.

    Hope this helps,

    Kind Regards,

    Matthew

    Add comment
    10|10000 characters needed characters exceeded