Hi,
I have a problem, every week a new order is generated automatically the firts week of the month. When I go to IP10 I can see that all the planned dates are the 1/1/19, 1/2/19, 1/3/19.. My question is if there is any way to change all the planned dates to the second week of the month. (The completion Requirment, is not activated).
Thank you
Have you tried to restart the plan and enter the 2nd week of the month as the new start date? In most cases, that should work.
Note that you should also be using scheduling indicator "Time - Key Date", or your dates will "drift" every month.