Now, I'm having some issues about defining settlement Receiver for PS.

- The first, I want to transfer cost of project to material. Therefore, I think I will have to define an object Settlement Receiver for PS.

- Second, I found TBO00 table to maintain Object but I don't understand the field in it's.

How do I have to process the Problem?

Help me, Please!

Best regards, Huy!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • May 27, 2010 at 09:48 AM

    1. Material is not a valid reciever for PS settlement.

    2. Donot use "Help me" , I dont think that is allowed as per forum rules.

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 06, 2010 at 07:37 AM

    Hi

    Maintain the settlement receivers (not material as it is not standard for a project/ WBS) in Project system -> cost-> Automatic and Periodic Allocations->Create Settlement Profile (the profile which you are using in OPSA). The table you indicated is defining an object as a settlement reciever (read object type - PD as project definition, PR as WBS element, NV as network/ activity etc).

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 24, 2010 at 04:37 PM

    Close the question!