we are facing a problem of MD04, Here we do not found Planed Order of reorder base Material. How can we convert Planed Order to Production ?
Fazle Rabbi
Fazle,
Run MRP for that material using transaction MD02, once this is done a planned order would get created which you can convert to Production order.
Incase you are still not getting planned order, please let us know the Reorderpoint set for the Material and its current stock and current production and planned order quantity.
Regards,
Prasobh