Dear Experts,

At the time of running MRP am generating scheduling lines which are specific to date whereas my requirement is to generate schedule lines month wise

How can I achieve this

Regards

Supergene

Accepted Solutions (1)

Accepted Solutions (1)

madlercm
Active Contributor
0 Kudos

MRP planning results are always for a specific date. This is the result of scheduling with lead time (either backwards or forwards) based on the requirement date.

So there no way around dates. Nevertheless, you can use a monthly lot size procedure, so you get one schedule line at the beginning of the month (look also at the lead time) for the requirements of the entire month.

Regards,

Mario