Cost is not displaying in Cost tab

Former Member
0 Kudos

Hi experts

i make a breakdown maintenance order (iw31) , and use control key pm03 in operation for external service PR is generated by entering all the data , like vendor Purc. group, material group, service text , price , cost element , and then PR genreated

'but the plannig cost is not displying in cost tab

please guide where i am missing something

Regrds

Jitender

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi ,

Check whether in OIOF Costing Variant is assigned to your order type .

Check if cost elements are assigned to valuation categories

Check wehther the control key PM03 allows costing or no ..

Ensure cost element is maintained in the default value profile for PM External Operation data

regrds

pushpa

Answers (4)

Answers (4)

Former Member
0 Kudos

HI

thnks for everybody

Regards

Jitender

Former Member
0 Kudos

Hi,

Have you maintained the costing variant for the plant which you used first. Goto OKP6, click om PM01 if its not there define or copy from some other costing variant & double click on that.

Click Valuation variant & define the parameters for external processing then click valuation variant / plant define that for the required plant.

I hope this will help you.

Regards,

Maheswaran.

peter_atkin
Active Contributor
0 Kudos

Jitender

Go to the cost tab and click on the Rep Plan/Act button to see if your costs are displayed there.

If they are, then its a problem with your value categories.

If not, then check the Control tab to see if there are values in the CstgVariantPlan and CstgVariantActl field, If not, then see the posts above.

If neither of the above are relevant, then check the Operation Control Key to see if its relevant for costing

PeteA

Former Member
0 Kudos

hi experts

first of all thnks all of you for giving your valuable time

hi Pete

when i click on Rep Plan/Act button system gives me message order has no cost

then i go to control tab

Parameters

Costing Sheet Status Profile

Overhead key PriorityType PM

CstgVariantPlan Category

CstgVariantActl MaintProfile 0000001

RA Key ExternProfile 0000002

Op./act. incrmt Mat.Profile 0000001

Here no data was in parameter

then i made a another order in sam eclient but for +_different plant_+ and in that order cost was updated

Cost was displaying for that plant

and following data in parameter in control tab

Costing Sheet PP-PC1 Status Profile

Overhead key PriorityType PM

CstgVariantPlan PM01 Category

CstgVariantActl PM01 MaintProfile 0000001

RA Key 000001 ExternProfile 0000002

Op./act. incrmt 0010 Mat.Profile 0000001

now pls suggets where i am missing

Regards

Jitender

peter_atkin
Active Contributor
0 Kudos

These are the standard PM/CS Order settings for costing:

- CstgVariantPlan PM01

- CstgVariantActl PM01

You can set these values as follows:

->IMG

-->Plant Maintenance and Customer Service

--->Maintenance and Service Processing

-


>Maintenance and Service Orders

-


>Functions and Settings for Order Types

-


>Costing Data for Maintenance and Service Orders

-


>Assign Costing Parameters and Results Analysis Keys (TCode OIOF)

PeteA

Former Member
0 Kudos

Hi,

Check whether you have maintained costing variant for Maintenance plant. Go to OKP6, there you have to maintain costing variant for the plant.

Regards,

Maheswaran.