Hi guys.

We have an issue whereby we have breaks defined against the HR employee (TCode PTMW) as per corporate HR requirements.

However, when we plan splits against the operations we do not want the dates/times to be rescheduled according to these HR breaks.

-


Example: HR break is between 12:00 and 13:00 If we plan a 2H split in the PM/CS order starting at 11:30, then the system reschedules the end time to 14:30 We want it to be 13:30 as the tecnicians lunch break times are flexible

-


Any ideas how to disable this HR/PM integration?

Note: we have opened an OSS Message to SAP and are awaiting a response

PeteA

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Pete,

I am not sure if this would work for splits but have you tried De-selecting the "scheduling with breaks" indicator in OPU7 for the Plant/Order type combination?

Regards

Narasimhan

peter_atkin
Active Contributor
0 Kudos

Narasimhan

We tried that (and other things) without any success

The answer from SAP is to use External Scheduling