on 05-25-2010 7:17 AM
Dear All,
I have certaion activities like civil work,piping work in my project . Based on the work progress I will do the Quality check and after approval from third party agency or internal quality checks I will proceed.Pls is there way to map this scenerio in SAP.
Regards,
Manoj
Hi,
In standard SAP, there is no provision of carrying out inspection against Projects.
We had a similar requirement of carrying out inspection after project or during project, so what we did was:
- Created an audit via Audit Management Functionality.
- assigned project number / WBS as "Object Type" in the Audit.
- And then carried out the audit.
So we worked around with this option
Thanks
SUMIT
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.