What are all the cut over activities comes under PP module only

Accepted Solutions (1)

Accepted Solutions (1)

Dsk
Active Contributor
0 Kudos

1. Uploading of the Demand in the PIR ( MD61)

2. Open Production orders - Not started to produciton

3. Partially confirmed production order - In this case the material stock and also the operation confirmation has to be properly

mapped.

4. Stock in the WIP materials

5. Check the Shift Timings ( for any recent changes)

Above are the few PP - Cutover activities, Apart from all the master data upload in the Production system

Reg,

Dsk

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Gopi,

Pl. go through some useful links on cutover -

http://www.sap-img.com/production/pp-questions-answers.htm

http://www.sap-img.com/production/pp-questions-answers.htm

http://www.sap-img.com/sap-implementation.htm

It will be help in understanding cutover of PP module.