Skip to Content
avatar image
Former Member

Automatic creation of inspection lot after UD

Hello,

My clients wants an automatic creation of inspection lot after a UD valuated to rejected. The inspection lot should have the same properties as the preceding one.

Is it possible in standard? and if yes, how can i do this?

Thanks,

Aurélien

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 30, 2016 at 04:39 PM

    No, it s not really standard.

    You would need to create a follow-up action that is attached to your rejected UD code. Have the follow-up action post the material from blocked, (or whereever you are posting it to), back into QI. You'll need to have the 08 inspection type setup for the materials.

    You can' t create the same inspection type, (I'm assuming you have 01's or 04's). You could have the follow-up action create them, but since they would have to be created via QA01, the resulting lots would not be stock relevant.

    If you want to reinspect, an option is to use inspection points for your 01's or 04's and simply create a new inspection point within the same inspection lot. You would evaluate the first inspection point as rejected.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 30, 2016 at 04:53 PM

    Hello,

    thanks for the answer. I'm going to try the inspection point since our client want to avoid specific !

    Add comment
    10|10000 characters needed characters exceeded