Hi Experts
I am trying to see whether the delivery date of PR item is determined from PIR in case of source assigment is done. But this is not happening. Is there any clue?
I am looking for this because, the realistic possible date to be determined and to be known to user before processing the PR further.
Warm regards
ramSiva
Hi,
The delivery date taking into account the
-planned delivery time in the material master record (Preq created manually)
-purchasing department processing time (T399D-BZTEK) from the materials planning
EXIT_SAPLMEREQ_005 allows you to change the delivery date according to your requirements.
br,Gabor