Jan 20, 2019 at 12:14 AM

Planned Orders - Understanding Engineering/Design/Route changes during Firm Status

47 Views

SAP gurus,

Your assistance is greatly appreciated with a business matter I have come across, First a business example that will help with the matter at hand. Order 'X' was firmed for release on 1/19, a change to the MPI, including results sheets was submitted on the previous day and pushed into SAP, the traveler rolled the Rev accordingly, however the MPI did not, which resulted in a delta between the inspection lot and DHR BOM overview. I have read that firmed orders are static, however i have observed that changes will adopt the new specifications with the following MRP run. Can someone please help me understand the standard design better?