on 05-24-2010 3:45 AM
Hi, there,
I posted ths issue at SCM-PP forum but coudn't get proper answer.
I am working on multi-level material variants with order BOM process. The configurable header material and assembly should be
replaced by material variants after configuration is done. I configured the multi-level BOM explosion at sales order. After I configured the assembly, I executed type matching and a material variant for assembly was found. But the system didn't replace
configurable assembly with material variant automatically and I couldn't find any functionality to carry out replacement. The header material was replaced by material variant in sales order entry. However, while I tried to carried out technical processing to
create order BOM (CU51), the error message shows that I couldn't create order BOM due to the header material has been replaced
with material variant. Does anyone have experience at multi-level material variants with order BOM process? Please kindly help.
Thanks.
B. Regards,
Nancy
Please try to don't do the type matching for the header material in sales order before you create the order BOM in CU51.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.