Adding strategy to plan is not possible

Hi guys,

I'm trying to add a strategy to the inspection plan, for the sake of stability study on IDES.

I normally used to make it with no problems with best practices, I create the plan, then in trx CWBQM at the header level I add the strategy, then an the operation level in trx CWBQM I start to assign packages of the strategy to the operation.

The problem is that in IDES I'm not able to make the step of assigning packages to the operation, I used to see the icon (LAMP) of maintenance packages, beside inspection characteristics, at the operation level, but in IDES this icon is not present, so I'm not able to assign packages to the operation.

Does any body have any idea how can I solve this issue?

Regards,

MaX

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    May 24, 2010 at 02:43 PM

    Max,

    If you have a chance, check the Badi's that have been implemented in the two systems. In particular, you probably should look at the ones under Quality Planning,

    particulary: Business Add-In for Menu Enhancements in the EWB

    You might also check the Badi's under the Stability Study area as well. I'm not sure if any of these apply but you may find you need to work with some of these to get what you are seeing. In IDES sometimes not all the available BaDi's are actually implemented in some areas.

    These are just ideas. I'm not sure you'll actually find the problem here but it is where I would start looking.