Return STO process

Former Member
0 Kudos

Hello Friends,

After the return STO line is added and the delivery created and PGI'd by plant - MMBE displays the ink material in both plants - the plant and the TO BE receiving plant. Once the Return STO Delivery is PGR'd at 2TE1 MMBE displays correctly.

Can anybody help me on this?

Thanks,

Nilesh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member182609
Active Contributor
0 Kudos

Only the difference in STO return cycle in return po there is Return check box indicator should active.

Issue good from returning plant (Through MIGO 161 mvt type)

Then delivery VL10B Picking and PGI process is STD. once this activity completed return stock will update in supplying plant.