05-20-2010 3:45 PM
Dear Colleagues
I have a test system AAB and a production system AAP
I have a job with 40 steps and 40 different programs setup in AAB
Now I have to create the same job in AAP
I'd like to know if its possible to copy a variant of a program from a system to another
Thanks and Regards
05-20-2010 6:18 PM
Hi,
the variants can be transported using the RSTRANSP report.
In the selection screen specify report names and variants; after that the system will prompt for the WB request.
Regards,
Andrea
05-20-2010 5:04 PM
Hi,
If I understand correclty you can save the variant as a system variant by having the followng prefix for the variant name: CUS&
The system will ask for a transport when a variant name start with CUS&
Thanks
05-20-2010 6:18 PM
Hi,
the variants can be transported using the RSTRANSP report.
In the selection screen specify report names and variants; after that the system will prompt for the WB request.
Regards,