Subcontracting components getting separated

Former Member
0 Kudos

Hi Seniors,

We are having a subcon po for a header material XXXXX with quantity 380 cs and providing 2 components A & B of 2 ea. we have done GR for 380 cs as 190 cs in 1st GR and 190 cs in 2nd GR and the components been consumed as 1 in A 1 in B for 1st GR with mov.type 543 and for the 2nd GR 1 in A and 1 in B. so both A& B of 2 ea is been consumed. But my questions is, how system is taking 1 ea in both A&B for both GR correctly. if i had put the GR as 150 cs and 150 cs and 80 cs. how it would have separated the components ?? how components are getting separated proportionately ? kindly clear me please.

regards,

jana

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

If you are ok with the answer.Please mark the Thread as answered and give point.

So that others wonot spent much time on this.

Murugesan

Edited by: MurugesanM on May 21, 2010 3:12 PM

Former Member
0 Kudos

Hi Seniors,

we are not giving the components manually in po. The components are from BOM. How its splitting itself according to GR made. Kindly clear me please.

Regards,

Jana

kunal_ingale
Active Contributor
0 Kudos

hi

supppose u given component as a nd b for item C

now u given ratio in bom for 100 C u need 50 a and 50 b

so when u do GR partial system will auto calculate the components

like for GR of 50 C 25 a and 25 b

regards

kunal

Former Member
0 Kudos

Suppose BOM has to produce 2 EA of FG if you need 4 EA of RM and Fixed indicator is not flagged then it will behav as blow

Assume Stock at vendor : 3 EA of RM

GR1 of 1 EA of FG will consume 2 EA of RM

GR2 of 1 EA of FG will consume 1 EA of RM (No error message )

But if BOM has fixed indicator then GR2 will get error message as it will expect 2 EA of RM as per BOM.

Splitting based on the BOM and Fixed indicator.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jana,

I donot know whether you are using BOM or just entering in the PO.

I assume that the Components are entered directly in the PO.In that case system treats this as BOM only.

Say example:

If you hv entered your Header Material as 5 qty

and the Components as

Compo 1=10 pcs

Compo 2 - 5 pkts

System does the calculation and understands like. for producting 1 qty of Header material system consumes Compo1 =1pc and Compo2 = 2 Pkts

when ever you do Goods receipt the system brings the correct quantity based on this calculation as a comsumed quantity.

Hope it's OK for you.

Mug

Former Member
0 Kudos

hi murugesan,

thanks for your reply. As per BOM it is working.

regards,

jana