CM21 Levelling question

Former Member
0 Kudos

Hi Experts,

When I dispach 3 or 4 orders, some of the orders are getting overlapped. I do not want them to overlap. Are there any options in the strategy so that it will not overlap? I am slecting plan schedule forwards. Please tell me how to fix this.

Regards,

Sachin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

After dispatching the for capacity, it will not overlapp for the same work center.

Check capacity is marked in control key, scheduling parameter for production order, planned order, in work center capacity header relevant to finite scheduling.

Please check & revert.

Regards,

Suhas

Former Member
0 Kudos

Hi Suhas,

I found out the problem. Actually I had not used the capcity relevent formula in the capacity tab of the w/c. Once I put it there everything is working as desired. I am marking closing this thread. Thanks for your response.

Regards,