Planned order Basic dates

0 Kudos

Dear All,

The sales order was input by the CSR on today the delivery date entered in the order was next day. Therefore, the planned order should have been todayu2019s date. This would give us enough time to manufacture the product and deliver to the customer as requested. But the planned get created for next day.

Planning strategy for material is 40 and MRP type is PD and Lot size EX and all scheduling parameters are 0 day.

Can you please update me the factors from sales order which affect planned order dates.

Regards,

p983331

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

What might be happening here is

The requirement date is tommorrow, so the system starts to backward schedule from tommorrow from 11:59:59 PM or (the workcenter endtime), & as all the factors are 0, including the inhouse time therefore the start date would also be the same.

If you are doing the lead time scheduling, it starts similarly in the above manner, maybe the the total hrs required to manufacture the product does not cross 1 day.Check for the start & finish time in the planned order, so that you know what time it is taking.

Regards

Mithun

0 Kudos

No we are not doing lead time scheduling and the all operation time is 2 hrs. system taking finish date next date and 24:00 hrs.

Regards,

SAP PQ

Answers (2)

Answers (2)

former_member196530
Active Contributor
0 Kudos

Dear ,

If you do not select Lead Time Scheduling -2 duing MRP run MD02 for your item , then system will consider the GR procesing time(MRP 2 view) , routing operation timing ( Exectuin time -processing , teardown , set up , wait time , move time ) and calcualte the dates .

Goto to Operation -doubleclik on the line item -select Dates -Check Operation related Lates Start and latest finsih date n time .

Check that and revert back .

Regards

JH

Edited by: Jiaul Haque on May 20, 2010 11:48 AM

0 Kudos

All operation times are 2:00 hrs

And the Lates dates are

Latest dates

Start 2010/05/19 22:30:00

Finish 2010/05/19 24:00:00

Regards,

SAP PQ

0 Kudos

On which factor from sales order, planned order is basic dates are depends. Because this things are happened for only one sales order. When I tried to replicate it, the planned order dates are working fine. i.e for next dayu2019s delivery date system generate planned order for todayu2019s day.

Regards,

SAP PQ

Former Member
0 Kudos

Hi

Basic dates depends on GR processing time, in house production time and opening period

In the material master two types of in house production times are available:

Lot-size Independent - (Integer values only) MRP 2 orWork Scheduling view

Lot-size Dependent - (real numbers - decimal) Work Scheduling view

also check SD processing time (pick/pack, Load, Transit)

regards

Dev

Former Member
0 Kudos

Hi,

As per the information below All operation times are 2:00 hrs

And the Lates dates are

Latest dates

Start 2010/05/19 22:30:00

Finish 2010/05/19 24:00:00

Note the timing of the finish time it is 24 hrs means next day that is why the planned order is showing next day. please check.

0 Kudos

Hi Rajasekhar,

The Finish date and time are 2010/05/19 24:00:00. For next day system show 2010/05/20 00:00:01. The sales order created for delivery date 19th on 18th. As we are using 0 day timing for each scheduling parameter (In house production time, Sch Margin Key, GR Processing time), so the planned order should be for 18th not 19th.

Thanks and Regards,

SAP PQ

Former Member
0 Kudos

Hi,

Kindly ,check the following

1. check the PIR's

2. Outstanding sales orders if any

3. Remove the firm indicator in planned order

4. Chedk the MRP-4 view of the matearial master for collective Requirements

5. If every thing is clear, run the MRP using the control parameters Planning Select 2 or 3 delete and adapt new planning

Former Member
0 Kudos

Hi,

Please check in-house production time in MRP2 is blank.

Regards,

Suhas

0 Kudos

Yes it is 0.

Regards,

SAP PQ