In correct planned cost in planning board

56 Views

Hi,

we have a problem for the planned cost in planned board. Though we are not modifying any data, our user is trying to recalculate the costs in planning board using calculate costs button. then suddenly, the values on planned cost is disappearing for few activities and for some activities in correct value is appearing. But standard reports show value. They did not have the problem earlier. we are working on 4.6C.

I have checked the recent transports, some transports are related to value categories. Do these affect the cost plan display at planning board.But the reports show the correct values

Appreciate help in this regard