I would like to understand the behaviour of Minimum lot size in Quota arrangement while MRP run using quota arrangement split quantity.
Example scenario
Supplier1 - 60% - 70
Supplier2- 30% - 40
Supplier3 - 10% - 20
Total quantity required is 100. In this scenario which are the suppliers selected and what are the quantities. Assuming 70,40,20 above are Min lot size.
Any link to standard SAP functionality will help us.