Hi All,
SRM 5.0 SP13 ECS
We have PO change approval workflow set up in such a way that only if total value is increased on the PO,it should route for approvals otherwise no approval required. We also implemented couple of OSS notes to display the approvals for historic and current versions. Everything is working fine,but for one test the approval for historic version shows Error :click here for details (Graphical view) and if I select the table view,it says No approval required,which is not right.
Ex: PO with two line items goes through n step approval process.
For the first change, I changed delivery dates on the PO, which did not trigger any approval workflow (As expected)
For the second change, I decreased the dollar amount on the PO, which did not trigger any approval workflow (As expected)
Now if am looking at versions for the PO.
I have 3 historic versions and a current version for the PO
If i select historic version 1 and then click on the aproval tab..it shows error:click here for details, when i click on the details, it shows me a Java console error.
If i select the historic version 2 or 3 or current ..It shows me o step approval ,which is as expected.
But for historic verison which has gone through n step approval, it doesnt show me the approval chain.
Could this be Java applet issue on my machine. Any inputs/oss notes regaring this issue would be highly appreciated.
Thanks in advance!!