Hi All,
I have just joined a Project which is Going-Live the next week.
The last consultant has done almost nothing with respect to Data Collection related with Material Master, Opening Stock.
The Material Data which was given to me was till December 2009, which I had uploaded on the Production Server.
Today I got to know that there are more that 3000 Material which have not been uploaded in the Production Server & all these Materials are having Stock.
We are uploading Opening Stock as on 31.03.2010.
My concern is :
Can we Go-Live without uploading all the Material Master & there Opening Stock?
What we are planning is we will Go-Live as per our Schedule & and start Back-log Transaction like PO Creation, Goods Receipt & related activities starting from 01.04.2010 in the SAP system. In the meantime we will try to compile the Material Master their Stock. Once this is done, we will pen the Period March 2010 and upload the Material Master & the Stocks and again close the Period March 2010. Is this advisable?
Please guide.
Regards,