Hi,

Can sombody give me some tips?

The following is my perplexed thing:

Material Strategy group is 10.

Today is 2010-05-19, the stock is zero.

The material's planned delivery time is 30 work days .There is a LSF requirment 500 pc on 2010-05-19.

And also There is a 500 pc PO whose Delivery Date is 2010-07-20.

When MRP run,we find we get a PR whose purposed quantity is also 500 pc and Delivery Date is 2010-06-18.

However since there is a PO whose Delivery Date is 2010-07-20,we only need an Exception message number for the PO,not a PR after MRP run. In another client we can get what outcome we antcipate. But in this client we can not find where the problem is.Can somebody tell me where the problem is ?

Regards

chunhui