Hi Guru,

Maintenance cost has been allocated to maintenance order using activity type MAINT1 ( allocation cost element MAINT1_ACT , category 43) , but business wanted to post to a different allocation cost element. So I created a new activity type MAINT3 with new allocation cost element MAINT3_ACT, and try to use KB65 to do reposting ( see below ), but this doesn't seem to have option of updating the receiving allocation cost element, the sending and receiving cost element still pointed to MAINT1_ACT. Idealy, it should empty out the postings on MAINT1_ACT and post to MAINT3_ACT.

I also try to create reposting cycle, but don't know how to add activity type and cost element field on the receiver side. Please help if you can, thanks!!