Hi gurus,

I allocated maintenance cost to maintenance order using activity type MAINT1 ( allocation cost element MAINT1_ACT , category 43) , now I want to repost the cost to MAINT2 with a different allocation cost element MAINT2_ACT... so it should look like as below on the cost center report:

Dr. MAINT2_ACT

CR. MAINT1_ACT

I tried KB65 but it won't update the allocation cost element; I also try to create reposting cycle using KSC5, but I don't know how to add activity type and cost element field on the receiver side. Please help.