Shift Scheduling

40 Views

Dear Experts,

I have maintainted 2 shifts in my resource Starting from 0400 am to 1200 pm & 1200 pm to 0800 pm. As per my recipe process is scheduled for 20 hrs. I start order on 18th & it is scheduled to finish on 19th at 0800 am. Now i want to add another shift for this process from 0800 am to 0400 am so that instead of 19th it finishes on 18th itself on 1200 am. How can this be done without adding shift in the resource master data because this change will be for this order only..

Regards,