Preventive Maintenance Order - Observed Parameter value recording

Dear Sir,

We are generating Preventive Maintenance Order in SAP . As a part of business requirement , after the preventive maintenance action is completed by the maintenance person , he is also required to record the observed parameter values (e,g Observed Pressure Value / Observed Temperature / Current Value ) .

Please guide us the process to be followed in SAP so that these observed parameter values can be recorded against the reference Maintenance Order .

With Regards

B Mittal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 30, 2016 at 01:03 PM

    B Mittal

    1. Create measurement points for the equipment to be measured
    2. Create a task list and link a PRT with an assignment to the measurement point(s) above
    3. Create and schedule the maintenance plan to create orders
    4. Execute the orders including the creation of measurement documents for the PRTs created above.