Hi friends
i have created sales order for a material and estimated the cost of RS 100
during my G/R from production order system is picking the correct cost of 100
But when i changed some component of that particular material and estimated the cost for the same sales order .
Now the estimated cost for the particular sales order is 80 but still sytem is picking 100 which is wrong .
please suggest how to correct this .
when i am changing the cost estimate of particular sales order i am overwring the existing cost estimate .
In MBBS also stock is valueated at (100 ) old price .
Thanks