Production order with pipe line material

Former Member
0 Kudos

Production ordre created and got confirmed and found pipe line materials got stuck in COGI and on analysis found in that specific ordrer ordre pipe line material are not activated with special stock key indicator i.e. 4.

Due to this it got stuck in cogi and for the same material created an order and found there is a allocation and activated with special stock key indicator i.e. 4.

Help me to resolve the existing Goods issue from COGI and cause of not activated with special stock key indicator i.e. 4. in production order.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member196398
Active Contributor
0 Kudos

Jaya,

Its very simple, you need to go to COGI and excute it for Individual records, now select the record and click change details Icon (F5), now the goods movement record would be in editable mode. Here you would find a field "Special Stock", now assign value "P" and in the Vendor field enter the vendor number and then save, your goods movement would be posted.

Regards,

Prasobh

former_member196530
Active Contributor
0 Kudos

Dear ,

did the pipe line material is showing in production reservation as one of the BOM compoenent?

If it is the case , then cancel the confirmation in CO13 and try to connfirm the operation with Clear Reservation Option .

Refer the below thread which may help you to figure out the issue :

Regards

JH

Former Member
0 Kudos

provide me details process flow of production with pipeline material..