Hi,
I have a problem I would like to pose.
I have a project WBS elements and network activities. The activities are days long, and dates go, until then good. But I would like to put a percentage on a manual where I say as I think I've done the activity, I mean, for example, on a specific date to tell my advance of completion is 20% because I think that is so, it's like give a percentage of completed regardless of the dates on which the activity takes place. In the progress can not find this option. If I introduce a milestone, if there that I can put a percentage of progress but do not want to get a milestone for each activity. I am considering using user-defined fields to enter there is a percentage of manuals and the date on which the user enters the amount of progress or production. You help?
Thank you very much.