Skip to Content
0
May 18, 2010 at 07:11 AM

Mismatch between Actaul and Plan cost on Order

16 Views

Good Day;

We have the following issue in SAP that needs to be resolved.

When creating a work order it pulls the prices fort he materials from the maintenance planning plant.

The actual prices on goods issue is determined through the supply process which points to a different plant.

These materials is then issued directly to the order.

This results that the price from the planning plant is not updated and then a huge variance is created on the plan/actual cost on the PM order.

Is there a way that we can do the planning still in the planning plant, but use the supply process to extract the plan price from the plant that will be actually issuing the material.

The prices in the planning plant does not get updated as the stock is going directly to the order and not through theplanning plant where the plan prices comes from.

Thanks