I have create one IO and assign to project C0001, in CJ32, current budget and distributable for project c0001 is 2mil, I want to changed them to 1 mil, but I found them are all greyed out, we use budget distribution, how to change, IM32? or IM52? thanks.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 18, 2010 at 05:38 AM

    Use Txn IM52 and return 1Mil of budget for Investment measure.

    After that run the Txn IM38 to return the 1mil of buget fom position id & Invetment

    program