l have a environment with 1 NWDI Netweaver 7.0 SP20 (DDI), 3 EP system Netweaver 7.0 SP20 (EPD, EPQ & EPP) & Solution Manager 7 EHP1 (SMO). The latest guide "How to Setup CMS Service" talk about the using the CMS in SolMan to replace the CMS in NWDI, in this case, l still using the CMS in NWDI, therefore l can't refer to that guide.

l already setup CTS+ between DDI and SMO, the SMO is transport domain controller in this case. The DDI able to export the .SCA to the runtime system EPQ & EPP.

l would like setup Charm for for DDI and EP systems, in SOLAR_PROJECT_ADMIN, l would like to configure the System Landscape so that l can create the IMG project, what is the role for DDI, EPD, EPQ, EPP and SMO in this case, which system is Development, which is Production?

l am not able find any information describe about this.

Please advise.

Many Thanks

Jordan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    May 19, 2010 at 03:54 PM

    Hello,

    You don't know which system is production? Sorry, you have to know which is which.

    Please refer to the following SDN blog:

    /people/dolores.correa/blog/2009/06/05/cts-configuration-in-solution-manager-70-ehp1

    It provides a configuration guide for CTS+ integration with ChaRM.

    Best regards,

    Miguel AriƱ