Former Member
May 15, 2010 at 11:34 AM

Long term Planning - capacity issue

31 Views

Does any one have a way of running Long Term Planning in SAP.

When checking CM38 for production volumes, the start dates of

the planned orders always fall into the previous month from the

forecast (the monthly forecast is always placed on the first day

of the period and due to lead time scheduling the planned orders

to satisfy that forecast fall into the previous month). If i check the

capacity it show in same month for different month requirment.( it is clubing the requirment)

Though capacity scene was created from June to August , system shows loading from May month.

Month wise loading and availability are shown clubbed in capacity planning sheet.

Thanks in advanc....