Pick/pack time and loading time in route

HI People,

If I make entry in the shipping point that loading time and pick/pack time as route dependent then where do I enter these times in route as I didn't find any feild to enter these in routes.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    May 17, 2010 at 04:19 AM

    Hi Komal

    The pick pack time is maintained at a shipping point level. To update this go to the following:

    SPRO-Logistics Execution-Shipping-Basic Shipping Functions-Scheduling-Delivery scheduling and Trasnportation scheduling---Maintain Durations.

    Regards

    Indranil

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    May 17, 2010 at 06:49 PM

    You can control scheduling by sales doc type & shipping point. Logical path - Logistic Execution-shipping-basic shipping function -scheduling-delivery scheduling & Transportation sch.

    Trasportation planning will determine below mentioned fields.

    Check-in

    Loading start

    Loading end

    Shpmt completion

    Shipment start

    Shipment end.

    Picking, packing will be controlled by delivery scheduling

    give me ur email id will forward u the document for it

    Regards,

    Krishna O